Flight Week (April, 2004)
Seven members of the team went down to Johnson Space Center in Houston, where five were able to test the experiment in zero-gravity conditions aboard NASA's KC-135 'weightless wonder.'  The experiment proved successful and we achieved significant success with our ion drive design.  More info will be added soon on our results.

TEDP Submitted (February, 2004)
we have completed and shipped our Test Equipment Data Package to NASA for approval to fly the experiment on the KC-135.

Proposal Approved (December, 2003)
The proposal has been approved by NASA.  The team is now beginning to work on prototypes of the experiment and research designs and materials to use to construct the ion drive.

Proposal Shipped (October, 2003)
The proposal has been shipped to Houston and electronically submitted.

Proposal Complete (October, 2003)
After a long weekend the proposal is complete.  Document will be bound and shipped to Houston Monday night.  Pending approval from NASA, we will post a detailed equipment description at that time.   

Team Established (October, 2003)
Had initial group meeting and gained 14 people to the team.  Worked on design and started proposal.

New Project Conceived (September, 2003)
Andy and Tim began work on the new project.  Initial background research completed and conceptual design in works.