The Wisconsin Idea: Printing company uses
UW-Madison-developed methods to recover

Ananth Krishnamurthy, Omnipress vice-president of operations Tracy Gundert, and CEO David McNight

Ananth Krishnamurthy, Omnipress vice-president of operations Tracy Gundert, and CEO David McNight (large image)

In the difficult business climate following Sept. 11, 2001, leaders of Madison-based printing company Omnipress decided it needed a change. Specializing in conference material such as books, handouts, CDs or flash drives, Omnipress consistently finished orders on time, yet costs continued to rise. Then it implemented quick-response manufacturing (QRM): principles and methods for reducing product lead times from weeks to days, pioneered by Industrial and Systems Engineering Professor Emeritus Rajan Suri.

Omnipress started its QRM journey with the growing market for conference publications delivered on CDs. With the help of students in the Center for Quick Response Manufacturing, Omnipress reorganized its CD workflow around a “CD cell,” combining all CD-related operations on one team. Cell members were cross-trained to do almost every job, ensuring a flexible workflow. Within months, the company slashed the time staff took to prepare a conference-publications CD by 70 percent.

“We saw that the QRM principles worked. But to apply these very different principles to only one product we felt would be difficult, since most of our processes are integrated across multiple products,” says Omnipress CEO David McKnight. “We also anticipated we could get better efficiencies and results if we applied the concept to the whole company.”

Again, results were almost immediate. Within one quarter, the time to finish a print or digital job was on average cut by half. Before the reorganization, a bound book published via the offset printing process took almost 19 days from start to finish. Now, it is done in 10 or fewer days.

Connecting with
the College of Engineering

The UW-Madison College of Engineering welcomes inquiries from business and industry about solving technical problems, tapping into specialized exper tise or serving professional training needs. The college has a wide spectrum of industrial consortia, research centers and specialized services that are of direct benefit and support to industry. The college also is home to the largest professional development program in the nation, serving roughly 14,000 students annually. For more information, please contact:

With its QRM-inspired workflow in place, the company is well-positioned to weather economic storms ahead. The significantly shorter production times allows Omnipress customers more time to collect and submit their content — a powerful advantage in the competitive printing industry. At the same time, the reorganized workflow has reduced costs, increased revenue, uncovered hidden resources, and created new growth potential.

In fact, the QRM implementation transformed Omnipress from a fragmented operation to an agile competitor in a challenging market. For this reason, despite the recession and bad economic news, Omnipress vice president of operations Tracy Gundert remains optimistic. “Our organization is more in a state of openness towards change,” she says. “We don’t use the economy as an excuse. We continue to challenge ourselves to do better.”

During the past 15 years, more than 190 companies have implemented QRM in cooperation with the UW-Madison Center for Quick Response Manufacturing. “Omnipress’ success shows how QRM’s focus on lead time reduction strengthens competitiveness,” says Ananth Krishnamurthy, director of the QRM center. “The center provides companies like Omnipress a forum to learn about QRM and help in the transition from theory to practice.”